Case Study in Increasing Overall Equipment Effectiveness on Progressive Press Machine Using Plan-do-check-act Cycle
Publish Year: 1399
نوع سند: مقاله ژورنالی
زبان: English
View: 166
This Paper With 7 Page And PDF Format Ready To Download
- Certificate
- من نویسنده این مقاله هستم
استخراج به نرم افزارهای پژوهشی:
شناسه ملی سند علمی:
JR_IJE-33-11_016
تاریخ نمایه سازی: 6 اردیبهشت 1400
Abstract:
Press automotive components manufacturer in Indonesia with the Overall Equipment Effectiveness (OEE) achievement was ۶۰.۷%, it was below than world company level as mention in Japanese Institute of Plant Maintenance (JIPM)- Total Productive Maintenance (TPM) standard, the biggest OEE components problem was availability value that achieved ۶۳.۳%, then the biggest availability problem was dies preparation time. Using TPM method and Plan-Do-Check-Act (PDCA) cycle with Pareto chart and Fishbone diagram, we succeeded to improve dies setting time within one months. We could increase the availability value from ۶۳.۳% became ۶۷.۸% and finally OEE value increased from ۶۰.۷% became ۶۵.۳%.
Keywords:
Authors
C. Jaqin
Industrial Engineering Program, Mercu Buana University, Jakarta, Indonesia
A. Rozak
Industrial Engineering Program, Mercu Buana University, Jakarta, Indonesia
H. Hardi Purba
Industrial Engineering Program, Mercu Buana University, Jakarta, Indonesia
مراجع و منابع این Paper:
لیست زیر مراجع و منابع استفاده شده در این Paper را نمایش می دهد. این مراجع به صورت کاملا ماشینی و بر اساس هوش مصنوعی استخراج شده اند و لذا ممکن است دارای اشکالاتی باشند که به مرور زمان دقت استخراج این محتوا افزایش می یابد. مراجعی که مقالات مربوط به آنها در سیویلیکا نمایه شده و پیدا شده اند، به خود Paper لینک شده اند :