Bi-objective optimization model for integrated preventive maintenance and flexible job-shop scheduling problem
Publish place: 2nd National Conference on Indurtrial Engineering & Systems
Publish Year: 1392
نوع سند: مقاله کنفرانسی
زبان: English
View: 1,106
This Paper With 7 Page And PDF Format Ready To Download
- Certificate
- من نویسنده این مقاله هستم
استخراج به نرم افزارهای پژوهشی:
شناسه ملی سند علمی:
NIESC02_182
تاریخ نمایه سازی: 27 اردیبهشت 1393
Abstract:
This paper develops an integrated model for flexible job shop scheduling problem with the maintenance activities. Reliability models are used to perform the maintenance activities. This model involved twoobjectives: minimization of the makespan for flexible job shop production part and minimization of system unavailability for the PM (preventive maintenance) part. To aim the objectives, two decisions must be taken at the same time: assigning jobs on machines in order to minimize the makespan and finding the appropriate times to perform PM activities to minimize the system unavailability. These objectives are obtained with considering dependent machine setup times for operations and release times for jobs. Inadvance, the maintenance activity numbers and PM intervals are not fixed
Keywords:
Authors
Ezzat Atarodi
dept. Mazandaran university of science and technology
Javad Rezaeian
dept. Mazandaran university of science and technology
Ali Taheri
dept. Mazandaran university of science and technology
مراجع و منابع این Paper:
لیست زیر مراجع و منابع استفاده شده در این Paper را نمایش می دهد. این مراجع به صورت کاملا ماشینی و بر اساس هوش مصنوعی استخراج شده اند و لذا ممکن است دارای اشکالاتی باشند که به مرور زمان دقت استخراج این محتوا افزایش می یابد. مراجعی که مقالات مربوط به آنها در سیویلیکا نمایه شده و پیدا شده اند، به خود Paper لینک شده اند :