Optimized Resource Allocation in Construction Projects Using LOB Scheduling

Publish Year: 1395
نوع سند: مقاله کنفرانسی
زبان: English
View: 485

This Paper With 10 Page And PDF and WORD Format Ready To Download

  • Certificate
  • من نویسنده این مقاله هستم

استخراج به نرم افزارهای پژوهشی:

لینک ثابت به این Paper:

شناسه ملی سند علمی:

CCIVIL01_116

تاریخ نمایه سازی: 21 شهریور 1395

Abstract:

The substantial factor in the Line of Balance (LOB) Scheduling is repetitive characteristic of activities. Learning phenomenon in projects with repetitive characteristics causes increment in crew’s performance and therefore in the rate of production of activities. In many projects, such as road construction, one crew participates in more than one activity, through the project term. To make the balanced schedule, required work hours of common crews varies in all units because of learning phenomenon. In this paper by establishing a balanced schedule, a method for optimized resource estimation and allocation in road construction project is developed.

Authors

Mohammad amini

School of Civil Engineering, College of Engineering, University of Tehran, Tehran, Iran

gholamreza heravi

School of Civil Engineering, College of Engineering, University of Tehran, Tehran, Iran

مراجع و منابع این Paper:

لیست زیر مراجع و منابع استفاده شده در این Paper را نمایش می دهد. این مراجع به صورت کاملا ماشینی و بر اساس هوش مصنوعی استخراج شده اند و لذا ممکن است دارای اشکالاتی باشند که به مرور زمان دقت استخراج این محتوا افزایش می یابد. مراجعی که مقالات مربوط به آنها در سیویلیکا نمایه شده و پیدا شده اند، به خود Paper لینک شده اند :
  • Arditi, D., Tokdemir, O. B., and Suh, K. (2002). Challenges ...
  • Hegazy, T., and Wassef, N. (2001). _ Optimization with Repetitive ...
  • Amini, M., and Heravi, Gh. R. (2009). Schedule Compression for ...
  • Arditi, D., Tokdemir, O. B.. and Suh, K., (1999). Effect ...
  • نمایش کامل مراجع