Construction Project Delay Risk Assessment Based on ۴M۱E Framework and Afghanistan Situation

Publish Year: 1403
نوع سند: مقاله ژورنالی
زبان: English
View: 37

This Paper With 17 Page And PDF Format Ready To Download

  • Certificate
  • من نویسنده این مقاله هستم

استخراج به نرم افزارهای پژوهشی:

لینک ثابت به این Paper:

شناسه ملی سند علمی:

JR_CEJ-10-1_006

تاریخ نمایه سازی: 2 اردیبهشت 1403

Abstract:

In the realm of construction project management, delays present a significant impediment, particularly within complex socio-political contexts such as Afghanistan. This study endeavors to elucidate the multifaceted nature of construction project delays in Afghanistan, employing the ۴M۱E (Man, Machine, Material, Method, and Environment) framework to conduct a comprehensive risk assessment. The research methodology entailed the development of a structured questionnaire grounded in an extensive review of pertinent literature, targeting ۳۰ recognized causes of project delays. This instrument was administered to a representative sample of ۱۴۴ professionals across the Afghan construction industry spectrum, including clients, consultants, and contractors. Analytical rigor was applied through the deployment of frequency, severity, and importance indices to evaluate the collected data. This analysis culminated in the distillation of ten paramount delay risk factors, encapsulating elements such as governmental policy stability modifications in project scope and design alongside delays in material testing and approval processes. A comparative dimension was incorporated to benchmark these findings against global standards, thereby enhancing the robustness of the study’s conclusions. Moreover, the research delineates the congruence and discordance among different respondent cohorts, bolstering the integrity of the identified delay factors through a validation of internal consistency and reliability. The strategic application of the ۴M۱E framework, contextualized within the Afghan construction landscape, furnishes pivotal insights for stakeholders, equipping them with a nuanced understanding necessary for the proactive mitigation of delay risks. The implications of this study are far-reaching, promising to augment project completion efficiency, budget adherence, and overall project success, with particular resonance for environments paralleling the intricacies of Afghanistan. Doi: ۱۰.۲۸۹۹۱/CEJ-۲۰۲۴-۰۱۰-۰۱-۰۶ Full Text: PDF

مراجع و منابع این Paper:

لیست زیر مراجع و منابع استفاده شده در این Paper را نمایش می دهد. این مراجع به صورت کاملا ماشینی و بر اساس هوش مصنوعی استخراج شده اند و لذا ممکن است دارای اشکالاتی باشند که به مرور زمان دقت استخراج این محتوا افزایش می یابد. مراجعی که مقالات مربوط به آنها در سیویلیکا نمایه شده و پیدا شده اند، به خود Paper لینک شده اند :
  • Horta, I. M., Camanho, A. S., Johnes, J., & Johnes, ...
  • Abdulfattah, B. S., Abdelsalam, H. A., Abdelsalam, M., Bolpagni, M., ...
  • Wuni, I. Y., Shen, G. Q., & Hwang, B.-G. (2020). ...
  • Do, S. T., Nguyen, V. T., Tran, C. N. N., ...
  • Genc, O. (2023). Identifying principal risk factors in Turkish construction ...
  • Yong, Y. C., & Mustaffa, N. E. (2013). Critical success ...
  • Olawale, Y. A., & Sun, M. (2010). Cost and time ...
  • HYap, J. B. H., & Skitmore, M. (2017). Investigating design ...
  • Mukuka, M., Aigbavboa, C., & Thwala, W. (2015). Effects of ...
  • Gb, P. T., & Ajuwon, O. S. (2017). Effects of ...
  • Sambasivan, M., Deepak, T. J., Salim, A. N., & Ponniah, ...
  • Amoatey, C. T., Ameyaw, Y. A., Adaku, E., & Famiyeh, ...
  • Aibinu, A. A., & Jagboro, G. O. (2002). The effects ...
  • Nepal, M. P., Park, M., & Son, B. (2006). Effects ...
  • Yap, J. B. H., Rou Chong, J., Skitmore, M., & ...
  • Iqbal, S., Choudhry, R. M., Holschemacher, K., ALI, A., & ...
  • Alvand, A., Mirhosseini, S. M., Ehsanifar, M., Zeighami, E., & ...
  • Pham, H. T., Pham, T., Truong Quang, H., & Dang, ...
  • Shabani, R., Ishtiaque, T. A., Johansen, A., Torp, O., & ...
  • Niazi, G. A., & Painting, N. (2017). Significant Factors Causing ...
  • Bhih, M., & Hegazy, T. (2021). Multiple-window Modified But-For analysis ...
  • Jahanger, Q. K. (2013). Important causes of delay in construction ...
  • Bhih, M., & Hegazy, T. (2023). Multiple-window modified but-for analysis ...
  • Le-Hoai, L., Lee, Y. D., & Lee, J. Y. (2008). ...
  • Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. ...
  • Enshassi, A., Kumaraswamy, M., & Jomah, A. N. (2010). Significant ...
  • Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. ...
  • Akogbe, R. K. T. M., Feng, X., & Zhou, J. ...
  • Muhwezi, L., Acai, J., & Otim, G. (2014). An assessment ...
  • Hussain, S., Zhu, F., Ali, Z., Aslam, H. D., & ...
  • Wang, T. K., Ford, D. N., Chong, H. Y., & ...
  • Zidane, Y. J. T., & Andersen, B. (2018). The top ...
  • Li, X., Lu, W., Xue, F., Wu, L., Zhao, R., ...
  • Rezgui, Y. (2007). Exploring virtual team-working effectiveness in the construction ...
  • Kakar, A. S., Hasan, A., & Jha, K. N. (2020). ...
  • Qaytmas, N. (2020). Causes of Delays in Construction Projects in ...
  • Kakar, A. S., Hasan, A., Jha, K. N., & Singh, ...
  • Rao, P. B., & Joseph Camron, C. (2014). Causes of ...
  • Muneeswaran, G., Manoharan, P., Awoyera, P. O., & Adesina, A. ...
  • Ejaz, N., Ali, I., & Tahir, M. F. (2011). Assessment ...
  • Aibinu, A. A., & Odeyinka, H. A. (2006). Construction Delays ...
  • Obodoh, D. A., & Obodoh, C. (2016). Causes and effects ...
  • Alzara, M., Kashiwagi, J., Kashiwagi, D., & Al-Tassan, A. (2016). ...
  • Alinaitwe, H., Apolot, R., & Tindiwensi, D. (2013). Investigation into ...
  • Motaleb, O., & Kishk, M. (2013). An Investigation into the ...
  • Choplin, A., & Franck, A. (2016). Seeing Dubai in Khartoum ...
  • Alaghbari, W., Kadir, M. R. A., Salim, A., & Ernawati. ...
  • Khan, R. A., Gazder, U., & Qayoom, A. (2017). Comparison ...
  • Sambasivan, M., & Soon, Y. W. (2007). Causes and effects ...
  • Samarghandi, H., Tabatabaei, S. M. M., Taabayan, P., Hashemi, A. ...
  • Islam, M. S., & Trigunarsyah, B. (2017). Construction Delays in ...
  • Odeh, A. M., & Battaineh, H. T. (2002). Causes of ...
  • Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. ...
  • Al-Momani, A. H. (2000). Construction delay: a quantitative analysis. International ...
  • Bagaya, O., & Song, J. (2016). Empirical Study of Factors ...
  • Hsu, P. Y., Aurisicchio, M., & Angeloudis, P. (2017). Investigating ...
  • Marzouk, M. M., & El-Rasas, T. I. (2014). Analyzing delay ...
  • Toor, S.-U.-R., & Ogunlana, S. (2008). Problems causing delays in ...
  • Toor, S. ur R., & Ogunlana, S. O. (2008). Critical ...
  • Choong Kog, Y. (2018). Major Construction Delay Factors in Portugal, ...
  • Kazaz, A., Ulubeyli, S., & Tuncbilekli, N. A. (2012). Causes ...
  • Cho, K., Ahn, S., Park, K., & Kim, T. W. ...
  • Chan, D. W. M., & Kumaraswamy, M. M. (1997). A ...
  • Chan, D. W. M., & Kumaraswamy, M. M. (2002). Compressing ...
  • Ling, F. Y. Y., & Poh, B. H. M. (2008). ...
  • Hwang, B.-G., & Lim, E.-S. J. (2013). Critical Success Factors ...
  • Koushki, P. A., & Kartam, N. (2004). Impact of construction ...
  • Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay ...
  • Hair, J. F., Black, W. C., Babin, B. J., & ...
  • Abdul-Aziz, A. R. (2012). Control mechanisms exercised in Malaysian housing ...
  • Nguyen, T. P., & Chileshe, N. (2015). Revisiting the construction ...
  • Yap, J. B. H., Chow, I. N., & Shavarebi, K. ...
  • Maqsoom, A., Choudhry, R. M., Umer, M., & Mehmood, T. ...
  • Zarei, B., Sharifi, H., & Chaghouee, Y. (2018). Delay causes ...
  • Zaneldin, E. K. (2020). Investigating the types, causes and severity ...
  • Sinesilassie, E. G., Tabish, S. Z. S., & Jha, K. ...
  • Famiyeh, S., Amoatey, C. T., Adaku, E., & Agbenohevi, C. ...
  • Al-Kharashi, A., & Skitmore, M. (2009). Causes of delays in ...
  • Aziz, R. F. (2013). Ranking of delay factors in construction ...
  • Jahangoshai Rezaee, M., Yousefi, S., & Chakrabortty, R. K. (2021). ...
  • نمایش کامل مراجع