Optimizing Supplier Selection for a Construction Project by a Cash-Flow Approach Using a Hybrid Metaheuristic Algorithm

Publish Year: 1401
نوع سند: مقاله ژورنالی
زبان: English
View: 159

This Paper With 11 Page And PDF Format Ready To Download

  • Certificate
  • من نویسنده این مقاله هستم

استخراج به نرم افزارهای پژوهشی:

لینک ثابت به این Paper:

شناسه ملی سند علمی:

JR_BDCV-2-2_002

تاریخ نمایه سازی: 28 دی 1401

Abstract:

Supplier selection is the practice of evaluating and selecting the best or most suitable supplier for the organization based on the candidates' qualities and qualifications. In large construction projects, supplier selection strongly impacts the quality of materials as well as the cash-flow and logistical support of the project. The issue becomes particularly important when a high number and volume of orders and a varied set of items are involved. If the procurement process is organized into several periods, the impact of Net Present Value (NPV) on the project's overall profit or loss becomes significant, as well. In this study, the solution to a multi-product multi-period supplier selection optimization problem is evaluated using a hybrid metaheuristic algorithm and considering the cash flow. Our analysis of the results shows that the algorithm is able to obtain the intended outcome within an appropriate timeframe and with high precision.

Authors

Seyyed Esmaeil Najafi

Department of Industrial Engineering, Science and Research Branch, Islamic Azad University, Tehran, Iran.

Soheil Salahshour

Department of Industrial Engineering, Central Tehran Branch, Islamic Azad University, Tehran, Iran.

Bijan Rahmani Parchikolaei

Department of Mathematic, Noor Branch, Islamic Azad University, Noor, Iran.

مراجع و منابع این Paper:

لیست زیر مراجع و منابع استفاده شده در این Paper را نمایش می دهد. این مراجع به صورت کاملا ماشینی و بر اساس هوش مصنوعی استخراج شده اند و لذا ممکن است دارای اشکالاتی باشند که به مرور زمان دقت استخراج این محتوا افزایش می یابد. مراجعی که مقالات مربوط به آنها در سیویلیکا نمایه شده و پیدا شده اند، به خود Paper لینک شده اند :
  • Arani, H. V., & Torabi, S. A. (۲۰۱۸). Integrated material-financial ...
  • Weber, C. A., Current, J. R., & Benton, W. C. ...
  • Liu, S. S., & Wang, C. J. (۲۰۱۰). Profit optimization ...
  • Elazouni, A. M., & Metwally, F. G. (۲۰۰۷). Expanding finance-based ...
  • Zhang, X., Song, H., & Huang, G. Q. (۲۰۰۹). Tourism ...
  • Nydick, R. L., & Hill, R. P. (۱۹۹۲). Using the ...
  • Akarte, M. M., Surendra, N. V., Ravi, B., & Rangaraj, ...
  • Vokurka, R. J., Choobineh, J., & Vadi, L. (۱۹۹۶). A ...
  • Ghodsypour, S. H., & O’brien, C. (۲۰۰۱). The total cost ...
  • Singh, D. A., & Tiong, R. L. (۲۰۰۵). A fuzzy ...
  • Lam, K. C., Palaneeswaran, E., & Yu, C. Y. (۲۰۰۹). ...
  • Jaskowski, P., Biruk, S., & Bucon, R. (۲۰۱۰). Assessing contractor ...
  • San Cristóbal, J. R. (۲۰۱۲). Contractor selection using multicriteria decision-making ...
  • Elazouni, A. M., & Gab-Allah, A. A. (۲۰۰۴). Finance-based scheduling ...
  • Ali, M. M., & Elazouni, A. (۲۰۰۹). Finance‐based CPM/LOB scheduling ...
  • Abido, M. A., & Elazouni, A. M. (۲۰۱۱). Multiobjective evolutionary ...
  • Kelley Jr, J. E. (۱۹۶۱). Critical-path planning and scheduling: Mathematical ...
  • Hendrickson, C., Hendrickson, C. T., & Au, T. (۱۹۸۹). Project management ...
  • Siemens, N. (۱۹۷۱). A simple CPM time-cost tradeoff algorithm. Management science, ۱۷(۶), ...
  • Moselhi, O. (۱۹۹۳). Schedule compression using the direct stiffness method. Canadian ...
  • El-Rayes, K., & Moselhi, O. (۱۹۹۸). Resource-driven scheduling of repetitive ...
  • Leu, S. S., & Yang, C. H. (۱۹۹۹). GA-based multicriteria ...
  • El-Rayes, K., & Jun, D. H. (۲۰۰۹). Optimizing resource leveling ...
  • Hegazy, T. (۱۹۹۹). Optimization of resource allocation and leveling using ...
  • Chan, W. T., Chua, D. K., & Kannan, G. (۱۹۹۶). ...
  • Hartmann, S. (۲۰۰۱). Project scheduling with multiple modes: a genetic ...
  • Zhang, H., Tam, C. M., & Li, H. (۲۰۰۶). Multimode ...
  • El-Rayes, K., & Kandil, A. (۲۰۰۵). Time-cost-quality trade-off analysis for ...
  • El-Abbasy, M. S., Zayed, T., & Elazouni, A. (۲۰۱۲). Finance-based ...
  • Weber, C. A., Current, J. R., & Benton, W. C. ...
  • Liu, S. S., & Wang, C. J. (۲۰۱۰). Profit optimization ...
  • Elazouni, A. M., & Metwally, F. G. (۲۰۰۷). Expanding finance-based ...
  • Zhang, X., Song, H., & Huang, G. Q. (۲۰۰۹). Tourism ...
  • Nydick, R. L., & Hill, R. P. (۱۹۹۲). Using the ...
  • Akarte, M. M., Surendra, N. V., Ravi, B., & Rangaraj, ...
  • Vokurka, R. J., Choobineh, J., & Vadi, L. (۱۹۹۶). A ...
  • Ghodsypour, S. H., & O’brien, C. (۲۰۰۱). The total cost ...
  • Singh, D. A., & Tiong, R. L. (۲۰۰۵). A fuzzy ...
  • Lam, K. C., Palaneeswaran, E., & Yu, C. Y. (۲۰۰۹). ...
  • Jaskowski, P., Biruk, S., & Bucon, R. (۲۰۱۰). Assessing contractor ...
  • San Cristóbal, J. R. (۲۰۱۲). Contractor selection using multicriteria decision-making ...
  • Elazouni, A. M., & Gab-Allah, A. A. (۲۰۰۴). Finance-based scheduling ...
  • Ali, M. M., & Elazouni, A. (۲۰۰۹). Finance‐based CPM/LOB scheduling ...
  • Abido, M. A., & Elazouni, A. M. (۲۰۱۱). Multiobjective evolutionary ...
  • Kelley Jr, J. E. (۱۹۶۱). Critical-path planning and scheduling: Mathematical ...
  • Hendrickson, C., Hendrickson, C. T., & Au, T. (۱۹۸۹). Project management ...
  • Siemens, N. (۱۹۷۱). A simple CPM time-cost tradeoff algorithm. Management science, ۱۷(۶), ...
  • Moselhi, O. (۱۹۹۳). Schedule compression using the direct stiffness method. Canadian ...
  • El-Rayes, K., & Moselhi, O. (۱۹۹۸). Resource-driven scheduling of repetitive ...
  • Leu, S. S., & Yang, C. H. (۱۹۹۹). GA-based multicriteria ...
  • El-Rayes, K., & Jun, D. H. (۲۰۰۹). Optimizing resource leveling ...
  • Hegazy, T. (۱۹۹۹). Optimization of resource allocation and leveling using ...
  • Chan, W. T., Chua, D. K., & Kannan, G. (۱۹۹۶). ...
  • Hartmann, S. (۲۰۰۱). Project scheduling with multiple modes: a genetic ...
  • Zhang, H., Tam, C. M., & Li, H. (۲۰۰۶). Multimode ...
  • El-Rayes, K., & Kandil, A. (۲۰۰۵). Time-cost-quality trade-off analysis for ...
  • El-Abbasy, M. S., Zayed, T., & Elazouni, A. (۲۰۱۲). Finance-based ...
  • Elazouni, A. M., & Metwally, F. G. (۲۰۰۵). Finance-based scheduling: ...
  • onstruction research congress ۲۰۱۲: construction challenges in a flat world(pp. ...
  • Elazouni, A. M., & Metwally, F. G. (۲۰۰۵). Finance-based scheduling: ...
  • نمایش کامل مراجع