Procurement Management Challenges in Petrochemical Projects of Iran

Publish Year: 1387
نوع سند: مقاله کنفرانسی
زبان: English
View: 2,639

This Paper With 20 Page And PDF Format Ready To Download

  • Certificate
  • من نویسنده این مقاله هستم

استخراج به نرم افزارهای پژوهشی:

لینک ثابت به این Paper:

شناسه ملی سند علمی:

PPS03_014

تاریخ نمایه سازی: 17 شهریور 1387

Abstract:

Procurement-oriented problems are usual in petrochemical mega projects in Iran, unavoidably resulting in contractual claims and increased project time and cost. This study was aimed, first, at collecting the perceptions of petrochemical projects practitioners on how significant are the procurement-oriented problems; and, second investigating whether the recommendations stated by the said practitioners are applicable to and effective at mitigating the corresponding problems with reference to a ranking order established using the mean score method. It was also observed that problems related to external issues (especially those of financial aspects) had the most significance and problems related to human behavior had the least significance in the procurement process of petrochemical mega projects. It is believed that the findings can provide much more insight for the petrochemical mega projects practitioners as well as the researchers and thus help to improve the productivity and overall performance of the procurement processes of these projects in Iran.

Authors

Mohsen Vafaei

Senior Expert of Procurement Contracts (MAPNA MD-۳)

Mohammad Vafaei

Master student, Dept. of Industrial Engineering, Yazd University of Iran

Mohammad Saleh Oliaw

Associate Professor, Dept. of Industrial Engineering, Yazd University of Iran

مراجع و منابع این Paper:

لیست زیر مراجع و منابع استفاده شده در این Paper را نمایش می دهد. این مراجع به صورت کاملا ماشینی و بر اساس هوش مصنوعی استخراج شده اند و لذا ممکن است دارای اشکالاتی باشند که به مرور زمان دقت استخراج این محتوا افزایش می یابد. مراجعی که مقالات مربوط به آنها در سیویلیکا نمایه شده و پیدا شده اند، به خود Paper لینک شده اند :
  • Ku maraswamy, M. M., and Chan, D. W. M. (1998). ...
  • Laudon, K. C. and Laudon, J.P. (2002), Management Information Systems, ...
  • Lo T. Y. et al., 4Construction Delays in Hong Kong ...
  • Mansfield, N. R. et al. (1994). 4Causes of delay and ...
  • NPC Website < http://www. nipc. net/indexen. php> (Oct. 01, 2006) ...
  • O'Brien, J. J. (1976). Construction delay: Respons ibilities, risk and ...
  • Ogunlana, S. O. et al. (1996). 4Construction delays in a ...
  • Okpala, D. C., and Aniekwu, A. N. (1988). 4Causes of ...
  • Pickavance, K. (2000). Delay and disruption in construction contracts, 2nd ...
  • Sekaran, U. (1992). Research methods for business, 2nd Ed., Wiley, ...
  • American National Standard, ANSI/PMI 99-001, Project Management Body of Knowledge, ...
  • Murali Sambasivan, Yau Wen Soon, Causes and effects of delays ...
  • Essam K. Zaneldin, Construction claims in United Arab Emirates: Types, ...
  • G. Sweis. Et al., Delays in construction projects: The case ...
  • Sadi A. Assaf, Sadiq Al-Hejji, Causes of delay in large ...
  • A.A. Aibinu*, G.O. Jagboro, The effects of construction delays on ...
  • Terry Williams, Assessing Extension of Time delays On major projects, ...
  • Mohan R. Manavazhi, Dinesh K. Adhikari, Material and equipment procurement ...
  • Nina Modig, The division of responsibility for project supply, Journal ...
  • Sihem Ben _ ahmoud -Jouini. Et al., Time-to- market VS. ...
  • Van Truong Luu. Et al., Quantifying schedule risk in construction ...
  • نمایش کامل مراجع