Earliest Times of Events in Fuzzy Critical Path Analysis
Publish place: 5th International Project Management Conference
Publish Year: 1388
نوع سند: مقاله کنفرانسی
زبان: English
View: 2,006
This Paper With 11 Page And PDF Format Ready To Download
- Certificate
- من نویسنده این مقاله هستم
استخراج به نرم افزارهای پژوهشی:
شناسه ملی سند علمی:
IPMC05_151
تاریخ نمایه سازی: 25 تیر 1388
Abstract:
A new approach is proposed to solve the project scheduling problem under fuzzy environment.The idea is to apply a combination of linear programming formulation and Zadeh`s extension principle.Activities duration is assumed to follow L-R fuzzy numbers. A LP model is developed to calculate the earliest events time. The membership functions of earliest times of events are derived by calculating lower and upper bounds of earliest times in different a-cuts of fuzzy durations Finally, an example with activities duration following L-R fuzzy
numbers is presented to indicate the efficiency of the proposed approach.
Keywords:
Authors
Farzad Firouzi Jshsntigh
University of Sistan & Baluchestan
Abdul Sattar Safaei
Tarbiat Modares University
مراجع و منابع این Paper:
لیست زیر مراجع و منابع استفاده شده در این Paper را نمایش می دهد. این مراجع به صورت کاملا ماشینی و بر اساس هوش مصنوعی استخراج شده اند و لذا ممکن است دارای اشکالاتی باشند که به مرور زمان دقت استخراج این محتوا افزایش می یابد. مراجعی که مقالات مربوط به آنها در سیویلیکا نمایه شده و پیدا شده اند، به خود Paper لینک شده اند :